Preparatory works for Singapore's "Long Island" reclamation project will start in January 2027 in the waters west of Bedok Jetty, and the Urban Redevelopment Authority (URA) will open a new round of public focus groups on recreation and connectivity at the same time, URA and the Housing and Development Board (HDB) announced on 17 November 2026. East Coast Park stays open throughout. What the new land will be used for, including whether it will hold housing, has not been decided.
TL;DR
- Phase one of preparatory works begins progressively from January 2027 west of Bedok Jetty; the area east of the jetty waits until after the 2029 SEA Games.
- Beaches, exercise paths and tracks at East Coast Park remain open during the works, URA and HDB say.
- More than 15,000 people have given feedback since November 2023; new focus groups from January 2027 will look at recreation and connectivity.
What is the Long Island project?
"Long Island" is a working name for a planned stretch of reclaimed land off Singapore's East Coast. URA, Singapore's national land-use planning agency, describes it as an integrated solution: protecting the low-lying East Coast from rising sea levels through land creation, adding a new reservoir to strengthen water resilience, providing land for future needs and creating new recreational space. CNA reports the new land could span around 800ha. In its March 2026 update, URA put the potential reclaimed area at over 800 hectares, about twice the size of Marina Bay.
What will happen off East Coast Park from January 2027?
According to the URA and HDB release, works will start by removing seabed obstructions, followed by building temporary sand bunds and sand infilling. Vessels will operate off East Coast Park inside a work area marked by silt screens and floating barriers. Sea users are advised to keep a safe distance, and safety advisories will be posted at the park and on agency websites before works begin.
The earlier June 2026 announcement, as reported by Mothership, described phase one as roughly 570ha of water west of Bedok Jetty, around 7km long and up to 1km wide, and phase two as around 155ha east of the jetty. The agencies stress that the preparatory works "will not determine the eventual detailed design" of Long Island.
The sea east of Bedok Jetty stays available for water sports and major international sporting events, with works there starting only after the 2029 Southeast Asian Games. HDB has also been running land-based soil investigation rigs along East Coast Park since September 2026, which the agencies say are localised and temporary.
How can residents give feedback on Long Island?
URA will hold a new series of focus group discussions from January 2027 on two themes. "Recreation" looks at how Long Island could complement East Coast Park with new waterfront areas. "Connectivity" looks at links between Long Island, the city and the eastern region. Past suggestions include water sports on the future reservoir, beaches and nature-based solutions along the new coastline. Interested members of the public can register through URA's Long Island engagement page.
Why it matters for East Coast homeowners and buyers
For owners and buyers in Marine Parade, Bedok, Siglap and Tanah Merah, the practical point is that the shoreline will be a long-running work zone, with vessels and barriers visible offshore from 2027. Longer term, the project changes what sits between these estates and the sea. But no land use, housing yield, transport link or timeline for completion has been announced, so any claim about effects on property values is speculation at this stage. Readers tracking the east's land supply can follow recent Government Land Sales activity, including the record Upper Changi Road GLS bid, the Bedok site award and the East Coast Road site release.
What is not yet confirmed?
The final shape of the island, its reclamation profile, the mix of land uses, the cost and the completion date have not been announced. URA and HDB say these depend on ongoing environmental and engineering studies and on public feedback.
Frequently Asked Questions
When do Long Island preparatory works start?
From January 2027, progressively, starting in the waters west of Bedok Jetty. Works east of the jetty start only after the 2029 SEA Games.
Will East Coast Park close during the Long Island works?
No. URA and HDB say beaches, exercise paths and tracks will stay accessible and park facilities remain open throughout the preparatory works.
Will Long Island have new housing?
Not confirmed. The agencies say the island will provide land for future needs, but no specific land uses or housing plans have been announced.
Sources and method
This article is based on URA press release PR26-79 (17 November 2026, joint with HDB) and URA's 30 March 2026 Long Island update, with independent reporting from CNA (Koh Wan Ting, 17 November 2026) and Mothership (Chloe Loh, 30 June 2026) for phase areas. Property News Asia does not give property or investment advice.